Removable Iron PIT Installation Image
Removable Iron PIT Installation Image
- ROLL Type System L6,500*W2,500*H1,000
- GRATING Type System L6,500*W2,500*H1,000
Site Preparation |
1. Portable Automatic Tire Washer Installation Equipment : Forklift 7Ton or More, Excavator 0.8 ton or More 2. Supplementary Water Work : 1/2B(13mm) PIP or HOSE 3. Electric Entry Construction : Power 20kw 3Ø 380V or 220V, CABLE 660CV 22㎥ × 4C 4. Basic Construction(Digging a Trench, Floor Concrete Casting, Concrete Work on Entrance and Exit) 5. Vinyl Work on the Iron PIT Contact Surface Before Concrete Casting |
---|
-
01 Digging a Trench
-
02 Digging a Trench
-
03 Floor Concrete Casting
-
04 Installing the Portable Automatic Tire Washer
-
05 Backfilling Work
-
06 Formation of the Entry and Exit
-
07 Rebar Placing on the Entry and Exit
-
08 Concrete Casting on the Entry and Exit
-
09 Complete Installation and Pilot Operation